Construction Updates

Crack Filling Program


The Crack Filling program will start the week of August 10th. Work is expected to be completed in approximately 5 days.  Please see map below for construction areas.  Please use caution through construction areas.  Thank you for your patience and cooperation.

Crack filling map




























 

Your Annual Street Maintenance Program

 
The annual Street Resurfacing Program is expected to begin in mid-August, on nearly 2.82 miles of your Mokena streets. Due to the volume of work involved in this project, this work should take roughly 8-10 weeks.

The program contains five typical sequential stages:

  1. Sawcutting of the curbs and sidewalks on your street:  Make the cuts in the curbs and sidewalks where the old concrete will be removed and replaced.
  2. Removal and replacement of the curbs and sidewalks:  The old concrete is removed and new concrete is poured in its place.
  3. Grinding of asphalt:  2" of the old asphalt is taken off the top of the street through a grinding process.
  4. Pavement patching:  Any spots in the street that need extra attention are patched.
  5. A final new layer of asphalt is placed.

Once the first step is started and/or completed on your roadway, it could be a week or longer before the next step gets started.  While you may experience some inconvenience during construction, resurfaced streets are a positive outcome once completed. 

Below is a list of the streets that are part of this year's program, as well as a map.  Check back for updates on what work is being done in which areas.  Please contact us at (708) 479-3900 with any questions or concerns you may have about the program.  We appreciate your cooperation in improving our community!

Project Streets

Grasmere Subdivision

  • Kirkstone Way (south of 195th Street)
  • Bedford Ln
  • Lancaster Drive (south of 195th Street)
  • Trenton Way (south of 195th Street)
  • Stonehenge Drive (south of 195th Street)
  • Lindsay Lane
  • Royal Court
  • Cambridge Drive (west of Stonehenge Drive)
  • Derby Lane (west of Everett Lane)

Map of streets being resurfaced






















 

 

Annual Sidewalk Repair Program


Work will begin the week of August 24 on the annual sidewalk repair program. This year, approximately 6,500 square feet of sidewalk and approximately 500 lineal feet of curb and gutter will be removed and replaced. 

Please contact us at (708) 479-3900 with any questions or concerns you may have about the program.  We appreciate the opportunity to serve you!

 


Updated August 11, 2020

     
     
     

     
    Village of Mokena | 11004 Carpenter Street Mokena, IL 60448
    Phone: (708) 479-3900  |  Fax: (708) 479-4844
    Contact Us  |  Site Map   |  Powered by MunicipalCMS
    E-notify RSS Feeds 
     
    0