Construction Updates
Annual Street Maintenance Program

Last Updated:  July 25, 2016

Annual maintenance work is now underway on nearly 5 miles of Mokena streets.  Due to the volume involved, this work will take roughly 8-10 weeks to complete.

Mokena's street maintenance program contains five steps (outlined below), and is set up like an assembly line.

  1. Sawcutting of curbs and sidewalks.
  2. Removal and replacement of curbs and sidewalks.  Old concrete is removed and new concrete is poured in its place.
  3. Grinding of asphalt.  2" of old asphalt is taken off the top of the street through a grinding process.
  4. Pavement patching.  Any spots in the street that need extra attention are patched with asphalt.
  5. A final new layer of asphalt is placed.

Once the first step is started and/or completed on your street, it could be a week or longer before the next step gets started.  While you may experience some inconveniences during construction, resurfaced streets are a positive outcome once completed, and represent a lasting investment in our community's assets. 

Below is a list of the streets that are part of this year's program, as well as a map.  Check back weekly for updates on what work is being done in which areas.  Feel free to contact us at (708) 479-3900 with any questions or concerns you may have about the program.  We appreciate the opportunity to serve you!

Project Subdivisions/Streets

Marley Creek
  * 
Camden Court
  *  Dickens Drive
  *  London Lane
  *  Dilber Bay
  *  Jacob Drive (from London Lane to Chestnut Court)

Savannah Landings
  *  Quail Drive
  *  Kestrel Avenue
  *  Dove Avenue
  *  188th Place

Creekview West
  * 
197th Street (116th Avenue to Victorian Drive)
  * 
Westminster Drive
  * 
Kensington Drive
  *  Buckingham Drive
  *  Wembley Drive
  *  Victorian Drive (Townline Road to 195th Street)
  *  Greenview Avenue
  *  Roberts Road

Central Mokena
  *  Union Avenue
  *  Revere Road (Wolf Road to Midland Avenue)

Hickory Creek Drive

189th Street (Hickory Creek Drive to Jodi Road)

Old LaGrange Road

Map of Projected Road Work


Week of July 25-29, 2016

  • Contractor (PT Ferro) will be removing, framing, and replacing existing concrete curbs & sidewalks in the Hickory Creek and Old LaGrange Road area, Marley Creek and Savannah Landings.  Work could also begin in Creekview West near the end of the week.
  • Shotcrete work will be done in the Marley Creek, Savannah Landings, and Creekview West subdivisions.